Our grid-storage field guide is finally out
2,847
178 comments · 94 shares
Reactions
S
Helping mid-market operators cut interconnection lead time
Every time a storage guide drops, the comments turn into a fight about chemistry, and I find that exhausting — not because the arguments are wrong, they often aren't, but because the constraint almost never sits there. I've watched three projects stall on land control and one on a transformer order, and not one of them on cells. Reading the queue chapter first was …see more
Client Account Manager at Northlade Energy
Tobias, the transformer point matches what we're seeing in the Southwest — 62 weeks on the last order, and that was with a signed slot.